Building Trades Progress

We are now installing Hardee Plank siding and, at this point, we are about half done. The interior trim package and the kitchen, bathroom and laundry room cabinets have been delivered. Now when it rains we will have plenty to go in and do. We are also in the process of framing walls in the basement on rain days.

All the flooring, aside from the carpet, has been installed. This is something we needed before we could start the trim. The kitchen/breakfast and entry areas are all hardwood. The master bath is ceramic tile and the laundry room and hall bathroom are both vinyl.

The brick on the front porch and the fireplace is complete. The deck on the back of the house is almost complete. I believe we are still on schedule to completely finish our project by the last week of school.